Notes from CEBAF meeting on support structure for the Moller -- May 23, 1996

We (AG and DSD) had a meeting with Al Guerra.

*We need to get Al drawings of the quads and dipole.

*May want to use standard cartridges on dipole.

*Support structure should be built at CEBAF.

* Schedule:
two months from finish of design to complete job (construction, installation, alignment).
Freeze design third week of June, then need 60 days.

*10 kW for each quad, dipole power 120kW (300 V, 400 Amps). LCW from Hall A side.

*500 MCM cable needed for magnet power supplies, $5-10 per foot.

*Quad supplies in the Hall.

*Dipole power supplies maybe in Building 98, ``the Chalet''.

*Quads need klixons interlocked with power supplies.

*May want to support collimator box, etc from dipole support stand.

Respectfully submitted, 6/7, DSD.

Kirsten DeNoyelles
Mon Jun 10 15:29:39 EDT 1996